During the week of February 26, 2018, you will see the following activities:

  • Continued material and equipment deliveries;
  • Air monitoring near the drill rigs and waste containers;
  • Continued drilling activities transitioning from ERH electrode installation (185 of 227 planned electrodes installed to date) to monitoring well installation; and
  • Delivery and placement of major ERH treatments system components.

 

Site Safety:

Please be aware that this is an active and secured site.  Thank you for respecting the safety boundaries and please do not enter the site for any reason.