ERH treatment system operating measures as of October 29, 2018:

  • Average subsurface temperature was 101.5º C with a peak of 116.8º C.
  • The estimated TCE removal to-date is 5,451 pounds.
  • The perimeter air monitoring system has shown no TCE emissions at the perimeter of the site. The air monitoring results will be available on EPA’s website at https://cumulis.epa.gov/supercpad/cursites/csitinfo.cfm?id=0402598.

Please note that you may see occasional steam from the thermal treatment unit during system operation.  This is normal water condensation caused by weather conditions, and not a release of TCE vapor.

Site Safety:

Please be aware that this is an active and secured site.  Thank you for respecting the safety boundaries and please do not enter the site for any reason.

Additional Information:

If you have any questions regarding site activities, please see the contact section of this website.