Site Update – February 1, 2019:
On November 2018, CTS completed the Electrical Resistance Heating (ERH) treatment phase of the interim remedy and reduced TCE in soil, groundwater, and non-aqueous phase liquid (NAPL) by 95% in the treatment area. The ERH treatment system equipment has been dismantled and removed from the site. CTS is preparing for the next phase of the interim remedy, In-Situ Chemical Oxidation (ISCO), which is expected to begin in mid-2019.
Site Safety:
Please be aware that this is an active and secured site. Thank you for respecting the safety boundaries and please do not enter the site for any reason.
Additional Information:
If you have any questions regarding site activities, please see the contact section of this website.