Site Update – November 8, 2019:

During the week of November 4, 2019, CTS completed installation of 45 of 76 injection well casings planned for the site. Installation of additional injection well casings will continue next week.

 

Site Safety:

Please be aware that this is an active and secured site.  Thank you for respecting the safety boundaries and please do not enter the site for any reason.

Additional Information:

If you have any questions regarding site activities, please see the contact section of this website.