During the week of January 8, 2018, you will see the following activities:
- Continued material and equipment deliveries; air monitoring near the drill rigs and waste containers; and, installation of the ERH electrodes (34 of 229 planned electrodes installed to date).
- An additional drill rig will be on site to install emplacement wells for the ISCO Treatability Study.
- There will be a minor excavation along the outside perimeter of the site. This work will not impede traffic along Mills Gap road.