During the week of March 12, 2018, you will see the following activities:
- Resumption of ERH electrode installation (185 of 227 planned electrodes installed to date);
- Continued material and equipment deliveries;
- Relocation of the power supply line (new power poles and lines). One of the three new power poles will be installed in the DOT right-of-way outside the fence along Mills Gap Road. There will be some temporary traffic control during this installation; and
- Construction of the ERH system components on the surface of the site.
Site Safety:
Please be aware that this is an active and secured site. Thank you for respecting the safety boundaries and please do not enter the site for any reason.
Additional Information:
If you have any questions regarding site activities, please see the contact section of this website.