During the week of April 23, 2018, you will see the following activities: Continued ERH electrode installation (224 of 227 planned electrodes have been installed); Continued […]
During the week of April 16, 2018, you will see the following activities: Continued ERH electrode installation (221 of 227 planned electrodes have been installed); Continued […]
During the week of April 9, 2018, you will see the following activities: Continued ERH electrode installation (218 of 227 planned electrodes have been installed); Continued […]
During the week of April 2, 2018, you will see the following activities: Continued ERH electrode installation (205 of 227 planned electrodes have been installed); Continued […]
During the week of March 26, 2018, you will see the following activities: Continued monitoring well and ERH electrode installation (194 of 227 planned electrodes have […]
During the week of March 19, 2018, you will see the following activities: Continuation of monitoring well and ERH electrode installation (185 of 227 planned electrodes […]
During the week of March 12, 2018, you will see the following activities: Resumption of ERH electrode installation (185 of 227 planned electrodes installed to date); […]
ERH drilling activities (185 of 227 planned electrodes installed to date) will be suspended pending relocation of the power supply line. During the week of March […]
During the week of February 26, 2018, you will see the following activities: Continued material and equipment deliveries; Air monitoring near the drill rigs and waste […]